Timeline of Events

Date Event
7/15/2021 Submitted sketch plan review to York County
8/3/2021 Received York County comments to sketch plan review
12/9/2022 Submitted revised sketch plan application
12/13/2022 County rejected application for sketch plan review
5/23/2023 Traffic Impact Analysis (TIA) Submitted
6/30/2023 Submitted Nationwide Permit Application for site impacts
7/11/2023 Received response with comments for TIA
7/21/2023 Submitted site plan to York County and Office of School Facilities (OSF)
7/23/2023 Resubmitted TIA
7/28/2023 Received response from ACE requesting additional information
8/11/2023 Received response with comments for resubmitted TIA
8/23/2023 Received response from Department of Health and Environmental Control (DHEC) requesting additional information
8/25/2023 Submitted requested additional information to ACE
8/25/2023 Received denial from York County for site plan
9/5/2023 Submitted requested additional information to DHEC
10/12/2023 Received approval from Zoning Board of Appeals (ZBA) to waive buffer tree survey
10/16/2023 Received Daimler Blvd. encroachment permit (for school entrances)
10/16 - 20/2023 Conducted a second traffic study at W. Liberty Hill Rd. and Hwy. 274 and at Hwy. 49 and Hwy. 274
10/18/2023 Received second denial from York County for site plan
1/16/24 Received conditional approval of High School site plans